Project management is all about balance—timelines, budgets, and resources must align perfectly to ensure project success. But when you’re using Microsoft Project 2019 Pro, One of the most common and frustrating issues is resource over-allocation.

Resource overallocation occurs when a team member or resource is scheduled to work more hours than are available, resulting in burnout, missed deadlines, or budget overruns.

In this comprehensive guide, we will walk you through what resource overallocation is, why it happens, and—most importantly—how to fix it using the powerful features available in Microsoft Project 2019 Pro.

What is resource overallocation?

Resource overallocation occurs when a person, team, or equipment is assigned more work than they can handle within their available time. For instance, assigning a resource to work 16 hours a day when they’re only available for 8 hours causes an overallocation.

This issue can derail your schedule and even lead to project failure if not corrected early. Microsoft Project 2019 Pro provides several tools to detect, highlight, and fix these overallocations before they become critical.

Signs and Symptoms in Microsoft Project 2019 Pro

How can you tell if resources are over-allocated?

  • Red icons in the indicators columnA small red person icon appears beside tasks or resources. 
  • Red Text in Resource SheetResource names will appear in red to indicate overallocation. 
  • Team Planner View Shows ConflictsOverlapping bars or error markers. 
  • Overtime or excessive hours in usage views. 

These visual cues make it easy to spot and address overallocations before they escalate.

Why Overallocation Occurs

Understanding the root causes helps in long-term prevention:

  • Multiple Tasks Scheduled ConcurrentlyA resource assigned to two tasks at the same time. 
  • Unrealistic task durations or deadlinesDeadlines force stacked tasks. 
  • Incorrect resource calendarsNot accounting for holidays, part-time schedules, or leaves. 
  • Manually Scheduled TasksOverride automatic leveling and introduce conflicts. 
  • Lack of Visibility: Especially in large projects with hundreds of resources. 

How to Identify Overallocated Resources

Microsoft Project 2019 Pro offers several views and reports for spotting issues quickly:

a. Resource Sheet View

  1. Go to View > Resource Sheet. 
  2. Look for red-colored resource names indicating overallocation. 

b. Resource Usage View

  1. Go to View > Resource Usage. 
  2. Overallocated hours will be bold and red. 

c. Team Planner

  1. Use View > Team Planner. 
  2. Overlapping or red bars visually indicate scheduling conflicts. 

d. Task Usage View

Helps you understand how individual tasks are using each resource.

Solutions to Resolve Overallocations Step by Step

Method 1: Use the Resource Leveling Tool

Automatic Leveling

  1. Go to Resource > Leveling Options. 
  2. Select your leveling method: 
    • Manual or Automatic 
    • Day by day or week by week 
  3. Click Level All. 

This spreads out tasks to eliminate overbooking, but may alter your schedule.

Method 2: Manually reschedule tasks

  1. Use Task Usage or Gantt chart view. 
  2. Identify overlapping assignments. 
  3. Adjust start or finish dates to reduce workload overlap. 

Method 3: Assign Additional Resources

If a resource is overbooked:

  1. Open the task. 
  2. Go to Task Information > Resources. 
  3. Add another available resource and reduce units accordingly. 

Method 4: Modify Task Effort

Change the work instead of duration if too much effort is required.

  • Double-click task → Change Work (e.g., from 40h to 20h) 
  • Reduce the burden on the resource without extending time 

Method 5: Adjust Resource Availability

Set correct working hours:

  1. Resource Sheet > Resource Information > Change Working Time. 
  2. Adjust the calendar for holidays or part-time availability. 

Method 6: Split Tasks

Divide long tasks into parts and reschedule accordingly:

  • Use the Split Task button on the task toolbar. 
  • Drag a section to a new date. 

Method 7: Change Task Types

Task types affect scheduling:

  • Fixed Units 
  • Fixed Work 
  • Fixed Duration 

Adjust the type under Task Information > Advanced tab to see if the task becomes more flexible and reduces overallocations.

Best Practices to Prevent Overallocation

a. Plan resource calendars carefully

Customize working hours and avoid assigning resources during off-times or holidays.

b. Use constraints sparingly

Avoid excessive use of “Must Start On” or “Must Finish On” constraints, which limit flexibility.

c. Load balancing during planning

Use Resource Usage during initial planning to prevent overloads.

d. Regularly review team planner

Identify conflicts before they become bottlenecks.

e. Communicate with your team

Sometimes the best solution is offline—talk to the team and adjust based on availability.

Real-life scenarios and fixes

Scenario 1: One developer assigned to three tasks on the same day

  • FixUse Team Planner to drag tasks to non-conflicting time slots or add another developer. 

Scenario 2: Designer on Vacation, Still Assigned Work

  • FixEdit working time in their calendar. Reassign tasks or delay appropriately. 

Scenario 3: Overloaded Senior Engineer During Final Testing

  • Fix: Divide the task or add junior resources to assist. 

These real-life fixes can drastically improve the reliability of your project plan.

FAQs

Q1: What does the red person icon mean in Microsoft Project 2019 Pro?

It indicates that the resource assigned to the task is over-allocated—scheduled beyond their available working hours.

Q2: Does leveling always delay tasks?

Not always. If there is slack in your schedule, tasks can be rescheduled within the slack without delaying the project.

Q3: Can I ignore overallocation warnings?

It is not recommended. Ignoring them may cause delays, budget overruns, or poor resource management.

Q4: What is the best view to use when fixing overallocations?

Team Planner and Resource Usage offer the clearest insights into conflicts and workloads.

Q5: Can I prevent over-allocation using templates?

Yes. Starting with well-designed project templates helps avoid errors in task sequencing and resource assignments.